Office Move Timeline: 6 to 12 Month Plan by Phase With Checklist
9 min read ยท 2026-11-12
A realistic office move timeline starts 9 to 12 months before move day if you are leasing and fitting out a new space. If you are moving into a managed or serviced office, around 6 months is usually enough. Work backwards from your lease end date and plan in phases: strategy and budget, space and lease, design and IT, vendors and communication, final preparation, then move day and the first week after.
Office moves rarely slip because of the move itself. They slip because one task depends on another and nobody saw the chain. The lease is signed late, so fit-out starts late, so the network install misses its slot, and the team arrives in an office where nothing connects.
This guide is built to stop that. Every phase has an owner, a milestone you can check and the dependencies that decide whether the date holds. Use it as the plan you present to leadership, then adjust it to your team size and type of space.
The roadmap at a glance
Goal: Move the team into a working new office on the planned date, with IT live, the old space handed back and no lost working days. Duration: 12 months
Strategy and budget (12 to 9 months before)
Decide why you are moving, what the new space must do and what you can spend.
- Name a move project lead and a sponsor in leadership.
- Read the current lease: end date, notice period, break clauses and reinstatement duties.
- List requirements: headcount, desks, meeting rooms, hybrid days, location, access for staff.
- Draft the budget, including hidden costs and a contingency line.
Milestone: Leadership signs off on requirements, budget and target move date.
Space search and lease (9 to 6 months before)
Find the space and sign the lease with enough time left for fit-out.
- Shortlist spaces against your requirements and visit them with IT and facilities.
- Check the building's network options and when the provider can connect.
- Negotiate terms and run legal review on the new lease.
- Give notice on the current lease if the timing requires it.
Milestone: New lease signed and notice served on the old one.
Design, fit-out and IT planning (6 to 3 months before)
Turn the empty space into a place people can work in from day one.
- Approve the floor plan and seating plan.
- Brief the fit-out contractor and lock the build schedule.
- Order network lines, hardware and furniture with long lead times.
- Map every device, server and phone line that has to move or be replaced.
Milestone: Fit-out schedule confirmed and IT install date booked.
Vendors, operations and communication (3 to 1 months before)
Book everyone you depend on and tell people what is coming.
- Book the building elevator and loading dock for move day in both buildings.
- Hire movers and confirm insurance, packing and access rules.
- Announce the move to staff, then to clients and suppliers.
- Update address details with banks, insurers, payroll and online listings.
Milestone: Movers, elevator slots and IT install all confirmed in writing.
Final preparation (4 weeks to 1 day before)
Pack, label and test so move day is only logistics.
- Run a clean-out and decide what is sold, donated, stored or recycled.
- Hand out crates and labels tied to the new seating plan.
- Test network, Wi-Fi and phones in the new space before anyone arrives.
- Share a move day brief with times, contacts and who does what.
Milestone: Network tested in the new office and every team packed.
Move day and the first week (Day 0 to week 1)
Get people working fast, then close the project properly.
- Run the move in the agreed order: IT first out, IT first in.
- Keep the project lead and IT on site in the new office from the start.
- Collect issues in one shared list and fix them daily.
- Inspect the old space and start the handover and reinstatement work.
Milestone: All issues closed and the old space handed back.
How long does an office move take by type of space?
The type of space changes the length of your office relocation timeline more than anything else. Hubble's guide to moving office timelines gives these ranges.
For a full move, Oktra's office move checklist says most successful moves begin at least 9 to 12 months in advance. That matches the 12-month plan above, which leaves room for the search, the notice period and any delay in fit-out.
Team size matters too. A small team can often pack in a day. A large team needs a seating plan, a move order by department and often a weekend move.
- Leased office: the lease agreement takes 2 to 8 weeks to complete, then fit-out and furnishing take between one and two months.
- Managed office: fit-out and furnishing usually take between one and two months.
- Serviced office: you can move in right after signing, and companies can usually sign up to 3 months ahead of the start date.
- Coworking: day passes can be booked the day before.
The 6-month version for a managed or serviced office
If the provider handles the fit-out, you can drop the long lease and build phases. Your plan becomes mostly IT, communication and the move itself.
The old office does not get shorter. Even if the new space is ready in weeks, your notice period and the reinstatement of the old space still set the end date.
- 6 months before: name the project lead, read the old lease for notice and reinstatement duties, agree requirements and budget.
- 5 to 4 months before: shortlist and visit spaces, check network options with IT, sign the agreement, serve notice.
- 4 to 3 months before: agree the layout with the provider, book the elevator in your old building, list what IT has to move.
- 2 to 1 months before: book movers, announce the move to staff, then clients and suppliers.
- Last 4 weeks to week 1 after: the same final preparation, move day and fix week as the full plan.
Who owns what: roles for each phase
Give every phase one owner, even when several people do the work. One named person makes decisions move.
Put these names on the roadmap itself. When leadership sees an owner and a milestone next to each phase, the plan becomes something they can approve.
- Project lead: owns the plan, the issues list and the weekly status. Name this person at the very start.
- Leadership sponsor: approves requirements, budget and the decision points.
- Finance: owns the budget, the contingency line and the deposits and fees of both leases.
- Facilities or office manager: owns the space search, fit-out, furniture, movers and building access.
- IT: owns the network, hardware, phones, data backup and the test before move day.
- HR: owns staff communication, seating, accessibility needs and commute changes.
- Legal: owns lease review, notice dates and reinstatement duties.
The critical path: dependencies that move your date
Some tasks can slip without moving the date. Others push everything back. Those are your critical path, and they run in this order.
Add a buffer to each of these chains, not to the plan as a whole. Then set three decision points with leadership: after the lease (is the date still realistic?), after fit-out starts (is the budget holding?), and one week before the move (is the network tested? If not, the move waits).
- Lease signed before fit-out can start.
- Fit-out finished before IT can install cabling and equipment.
- Network live and tested before staff move in. IT is often the longest chain, because providers set their own install dates.
- Elevator and loading dock booked in both buildings. Gentle Giant's office move timeline puts elevator service in the old and new locations at 3 to 4 months before the move, and choosing movers at 1 to 2 months before.
- Old lease exit with notice served on time and reinstatement work planned.
Office move budget and hidden costs
Rent and movers are the costs everyone plans for. The ones that hurt are the others. Oktra's checklist names dilapidations on the current lease, temporary workspace or phased moves, technology upgrades, staff training and contingency as costs that are often underestimated. Dilapidations means returning the old office to the state your lease requires.
Build your budget in lines that match the roadmap phases, and ask finance to report spending against each line at every decision point. A budget that is only checked at the end cannot change the plan.
- Legal fees and deposits for the new lease.
- Fit-out, furniture and signage.
- Network install, new hardware and any overlap of two internet contracts.
- Movers, crates, storage and disposal of old furniture.
- Reinstatement of the old space.
- Temporary workspace if the dates do not line up.
- Staff time and training on new systems or building access.
- A contingency line for what nobody saw coming.
Communication plan: staff, clients and suppliers
People handle a move well when they hear about it early and often. Tell staff first, before clients or suppliers hear it from someone else. Then send updates at each milestone: lease signed, seating plan ready, packing instructions, move day brief, first day guide.
A short first announcement can look like this: "We are moving to our new office in the spring. Here is why, what changes for your commute and desk, and when you will hear more. Questions go to the move project lead." Keep each later update just as short.
For clients and suppliers, send one clear notice with the new address and the date it applies. Then update your website, email signatures, invoices, contracts, delivery accounts and online business listings in the same week.
Office move checklist for move day and the week after
Move day should be pure execution. Work through it in this order.
The project does not end when the van leaves. Plan a fix week. Keep one shared list for broken items, missing crates and IT problems, and review it every day. Then finish the handover of the old space, settle the last invoices and hold a short review of what went well and what to change next time.
- Before the movers arrive: IT shuts down and labels equipment, and the project lead checks access in both buildings.
- Loading: crates and furniture go out by department, following the labels and the seating plan.
- Unloading: IT equipment goes in first, then furniture, then crates to labelled desks.
- Setup: IT connects and tests every desk, phone and meeting room.
- Final walk: the project lead walks both spaces with the movers before sign-off.
Common mistakes to avoid
- Starting from the move date instead of the lease end date sets the plan too late, so count back from the notice period and the reinstatement deadline.
- Leaving IT until the last month puts the whole move at risk, so book the network install as soon as the lease is signed.
- Planning only the new space and forgetting the old one creates late costs, so put reinstatement and handover in the budget and the roadmap.
- Giving tasks to teams but no single owner slows every decision, so name one person per phase to keep decisions moving.
- Telling clients before staff damages trust, so staff should always hear first, and in detail.
- Closing the project on move day leaves problems open, so plan a fix week and a final review to catch what slipped.
Frequently asked questions
How far in advance should you plan an office move?
For a leased office with fit-out, start at least 9 to 12 months before, as Oktra recommends. A managed or serviced office can be planned in around 6 months, since the provider handles most of the setup. Whatever the new space, the exit from your old lease still depends on its notice period.
What is the first step in an office relocation?
Read your current lease. Its end date, notice period and reinstatement duties set every other date in the plan. Then name a project lead and agree on requirements and budget with leadership.
When should you book movers for an office move?
Gentle Giant suggests choosing movers 1 to 2 months before the move and scheduling elevator service in both buildings 3 to 4 months before. In a busy season or a busy building, book earlier and confirm access rules in writing.
How do you present an office move timeline to leadership?
Show the phases on one page, with an owner, a milestone and a date for each. Mark the critical path and the three decision points, and attach the budget by line. Leadership then approves a plan with clear checkpoints instead of a task list.